Processing, crushing, and screening 20,000 tons of concrete
Product conformed to ODOT 304 spec
GRAND AVE. LIMA OHIO
SEWER REHAB
Project Highlights & Scope:
Primary subcontractor on this $4.7 million 78” sewer rehab project
1,000’ of new 8” relief sewer 10-13’ deep
1,250’ of new 4” laterals
UTGARD-127-KOHNEN TILE
PIPE & CATCH BASINS
Project Highlights & Scope:
12,000’ of 8” to 30” pipe averaging 8-10’ deep
(5) new catch basins
Directional bore under US 127 and Tama Road, performed by subcontractor, Ruhenkamp Trenching & Boring
E.S. WAGNER COMPANY
CONCRETE CRUSHING
Project Highlights & Scope:
Processing, crushing, and screening 20,000 tons of concrete
Product conformed to ODOT 304 spec
CR 180 Drainage Improvements
STORM SEWER
Project Highlights & Scope:
300’ of 30” storm sewer
30” jack and bore under SR 658, performed by Underground Utilities, Inc.
Doghouse catch basin over ex. 66” RCP sewer
Swale grading/rock placement
Final grading, seeding and mulching
CR 300 DRAINAGE IMPROVEMENTS
STORM SEWER
Project Highlights & Scope:
Misc. open ditch clearing/cleaning
1,800 LF of 12” storm sewer installation
New headwall, (4) manholes, and (1) basin replacement
Relocate 15” concrete culvert
Jack & bore under CR 300
BEAVER CREEK
OPEN DITCH EROSION CONTROL
Project Highlights & Scope:
Haul & Place 9,000 ton of Type D Rip Rap
Haul & Place 14,100 ton of Type C Rip Rap
Steer Barn
SITEWORK & CONCRETE
Project Highlights & Scope:
Sitework and concrete for new 70x135 steer barn
735’ of walls ranging from 2’ to 8’
9,450 SF of floor
Subcontractors: F&S Concrete and Schnipke Excavating & Concrete during the floor pour
US 224 Water & Sewer Extension
STORM SEWER
Project Highlights & Scope:
1,200’ of 8” waterline extension
3 hydrants and 3 valves
8” water meter complete w/valve vault
1,200’ of 18” and 24” storm sewer extension w/2 new manholes
Napoleon Pool Demo
DEMOLITION
Project Highlights & Scope:
Complete demolition & removal of ex. pool
2,000 CY of concrete removal and disposal
Import, grade, and compact 2,000 tons of crushed concrete to stabilize the site
Misc. sitework and rough grading
rm sewer extension w/2 new manholes
BATY ROAD WATERLINE
WATERLINE
Project Highlights & Scope:
1,400’ of new 8” waterline extension
3 new fire hydrants
Utilized portable traffic signals to maintain one lane of traffic during construction
PLUM CREEK NATURE TRAIL PEDESTRIAN BRIDGES
STRUCTURAL CONCRETE
Project Highlights & Scope:
Construct a 62’ long x 8’ high redi-rock retaining wall
1,000 LF of open ditch reconstruction with brush removal & disposal
SOUTHSIDE STORM SEWER
STORM SEWER
Project Highlights & Scope:
1,100’ of new storm sewers 12” to 18” – ranging from 7-11’ deep
17 new storm structures
Lateral tie-ins
Complete alley removal and subgrade prep
2017 VARIOUS STORM SEWER IMPROVEMENTS
STORM SEWER
separate project sites in one contract – one site subcontracted Involves 6” thru 18” storm sewers – 2,300 LF total and 30 drainage structures – up to 10’ deep in Market St. area w/numerous existing utilities
RUDOLPH FOODS DITCH
RETAINING WALL & OPEN DITCH
Project Highlights & Scope:
Construct a 62’ long x 8’ high redi-rock retaining wall
1,000 LF of open ditch reconstruction with brush removal & disposal
FORT JENNINGS STORM SEWER
STORM SEWER
Project Highlights & Scope:
Replace 1,200 LF section of failing 30” storm sewer
Remove & dispose of existing pipe
Ranged from 10-13’ deep
FORREST STREET
WATERLINE REPLACEMENT
Project Highlights & Scope:
725’ of 6” waterline replacement – 140’ directional drill
Includes (2) hydrants, (3) valves, and 3” live tap
Install (3) new meter pits and residential tie-ins
LITTLE CRANKBERRY CREEK
OPEN DITCH
Project Highlights & Scope:
1 mile of selective tree cutting & logjam removal
2 miles of complete ditch reconstruction w/associated clearing & grubbing
10,000 CY of excavating & grading
Reconstruction of two lateral ditches/roadside swale
Includes culverts, erosion control structures, rock placement, and seeding/mulching
CATON DITCH
OPEN DITCH
Project Highlights & Scope:
2 miles of complete ditch reconstruction w/tree & brush removal
Reconstruction required the excavation of a maintenance bench to access the ditch due to the extreme width and depth of the channel
Includes logjam removal on the lower end
Approximately 20,000 CY of excavation & grading – 4.75 acres of seeding
WEBB RUN
OPEN DITCH
Project Highlights & Scope:
1 mile of selective tree cutting & logjam removal
2 miles of complete ditch reconstruction w/associated clearing & grubbing
10,000 CY of excavating & grading
Reconstruction of two lateral ditches/roadside swale
Includes culverts, erosion control structures, rock placement, and seeding/mulching
STEINLE DITCH
NEW WATERWAY
Project Highlights & Scope:
Construct 4 acre waterway, complete with seed & mulch and erosion control blanket
8,000 CY of excavating & grading
Haul & Place 110 ton of Type C rip rap
Install 43,200 SF of 16’ wide erosion control blanket
DUSTY ACRES DITCH
OPEN DITCH
Project Highlights & Scope:
56,000 CY of Excavation & Grading
Clearing & Piling of 6 miles of heavy trees & brush
Grading across 50 acres of farm ground
Clean 11 culverts & bridges
Seed 20 acres of ditch bank
Misc. Tile Repairs & Extensions
FORT JENNINGS STATE BANK
BUILDING DEMOLITION & SITE PREP
We were fortunate to be the demolition subcontractor on this local project that involved complete demolition and subsequent removal of the existing Fort Jennings State Bank. This bank was constructed in 1970 by Nolan’s Grandpa Bill ‘Banker Bill’ Wildenhaus...
GRESSEL DRIVE - WATERLINE
WATERLINE REPLACEMENT
Project Highlights & Scope:
Installation of 890 LF of C900 Waterline
(4) 45 Degree Bends
Pressure Test & Chlorinate the line
Expose, isolate, plug, and retest the line
Remove the plugs and reconnect to the existing lines using (3) solid sleeves