OUR WORK

Fenson Contracting works with both public and private clients on municipal, residential, agricultural, commercial, and industrial projects.

FAUROT PARK IMPROVEMENTS

SITE IMPROVEMENTS

Project Highlights & Scope:

  • Demolition & removal of existing playground
  • 600 LF of 12” storm sewer w/structures and 300 LF of curb drain
  • Overexcavation of ex. playground
  • Embankment for new playground

” laterals

WATER STREET IMPROVEMENTS

CURB & SIDEWALK REMOVAL & REPLACEMENT

Project Highlights & Scope:

    • 1,300 LF of 2” conduit installation for new street lights
    • 2,800 LF of curb removal
    • 2,900 LF of new type 2 curb & gutter
    • Misc. drive approach/sidewalk removal & replacement

GOMER SCHOOL DEMOLITION

DEMOLITION

Project Highlights & Scope:

  • Processing, crushing, and screening 20,000 tons of concrete
  • Product conformed to ODOT 304 spec

GRAND AVE. LIMA OHIO

SEWER REHAB

Project Highlights & Scope:

  • Primary subcontractor on this $4.7 million 78” sewer rehab project
  • 1,000’ of new 8” relief sewer 10-13’ deep
  • 1,250’ of new 4” laterals

UTGARD-127-KOHNEN TILE

PIPE & CATCH BASINS

Project Highlights & Scope:

  • 12,000’ of 8” to 30” pipe averaging 8-10’ deep
  • (5) new catch basins
  • Directional bore under US 127 and Tama Road, performed by subcontractor, Ruhenkamp Trenching & Boring

E.S. WAGNER COMPANY

CONCRETE CRUSHING

Project Highlights & Scope:

  • Processing, crushing, and screening 20,000 tons of concrete
  • Product conformed to ODOT 304 spec

CR 180 Drainage Improvements

STORM SEWER

Project Highlights & Scope:

  • 300’ of 30” storm sewer
  • 30” jack and bore under SR 658, performed by Underground Utilities, Inc.
  • Doghouse catch basin over ex. 66” RCP sewer
  • Swale grading/rock placement
  • Final grading, seeding and mulching

CR 300 DRAINAGE IMPROVEMENTS

STORM SEWER

Project Highlights & Scope:

  • Misc. open ditch clearing/cleaning
  • 1,800 LF of 12” storm sewer installation
  • New headwall, (4) manholes, and (1) basin replacement
  • Relocate 15” concrete culvert
  • Jack & bore under CR 300

BEAVER CREEK

OPEN DITCH EROSION CONTROL

Project Highlights & Scope:

  • Haul & Place 9,000 ton of Type D Rip Rap
  • Haul & Place 14,100 ton of Type C Rip Rap

Steer Barn

SITEWORK & CONCRETE

Project Highlights & Scope:

  • Sitework and concrete for new 70x135 steer barn
  • 735’ of walls ranging from 2’ to 8’
  • 9,450 SF of floor
  • Subcontractors: F&S Concrete and Schnipke Excavating & Concrete during the floor pour

US 224 Water & Sewer Extension

STORM SEWER

Project Highlights & Scope:

  • 1,200’ of 8” waterline extension
  • 3 hydrants and 3 valves
  • 8” water meter complete w/valve vault 
  • 1,200’ of 18” and 24” storm sewer extension w/2 new manholes

Napoleon Pool Demo

DEMOLITION

Project Highlights & Scope:

  • Complete demolition & removal of ex. pool
  • 2,000 CY of concrete removal and disposal
  • Import, grade, and compact 2,000 tons of crushed concrete to stabilize the site
  • Misc. sitework and rough grading

rm sewer extension w/2 new manholes

BATY ROAD WATERLINE

WATERLINE

Project Highlights & Scope:

  • 1,400’ of new 8” waterline extension
  • 3 new fire hydrants
  • Utilized portable traffic signals to maintain one lane of traffic during construction

PLUM CREEK NATURE TRAIL PEDESTRIAN BRIDGES

STRUCTURAL CONCRETE

Project Highlights & Scope:

  • Construct a 62’ long x 8’ high redi-rock retaining wall
  • 1,000 LF of open ditch reconstruction with brush removal & disposal

SOUTHSIDE STORM SEWER

STORM SEWER

Project Highlights & Scope:

  • 1,100’ of new storm sewers 12” to 18” – ranging from 7-11’ deep
  • 17 new storm structures
  • Lateral tie-ins
  • Complete alley removal and subgrade prep

2017 VARIOUS STORM SEWER IMPROVEMENTS

STORM SEWER

separate project sites in one contract – one site subcontracted
Involves 6” thru 18” storm sewers – 2,300 LF total and 30 drainage structures – up to 10’ deep in
Market St. area w/numerous existing utilities

RUDOLPH FOODS DITCH

RETAINING WALL & OPEN DITCH

Project Highlights & Scope:

  • Construct a 62’ long x 8’ high redi-rock retaining wall
  • 1,000 LF of open ditch reconstruction with brush removal & disposal

FORT JENNINGS STORM SEWER

STORM SEWER

Project Highlights & Scope:

  • Replace 1,200 LF section of failing 30” storm sewer
  • Remove & dispose of existing pipe
  • Ranged from 10-13’ deep

FORREST STREET

WATERLINE REPLACEMENT

Project Highlights & Scope:

  • 725’ of 6” waterline replacement – 140’ directional drill
  • Includes (2) hydrants, (3) valves, and 3” live tap
  • Install (3) new meter pits and residential tie-ins

LITTLE CRANKBERRY CREEK

OPEN DITCH

Project Highlights & Scope:

  • 1 mile of selective tree cutting & logjam removal
  • 2 miles of complete ditch reconstruction w/associated clearing & grubbing
  • 10,000 CY of excavating & grading
  • Reconstruction of two lateral ditches/roadside swale
  • Includes culverts, erosion control structures, rock placement, and seeding/mulching

CATON DITCH

OPEN DITCH

Project Highlights & Scope:

  • 2 miles of complete ditch reconstruction w/tree & brush removal
  • Reconstruction required the excavation of a maintenance bench to access the ditch due to the
    extreme width and depth of the channel
  • Includes logjam removal on the lower end
  • Approximately 20,000 CY of excavation & grading – 4.75 acres of seeding

WEBB RUN

OPEN DITCH

Project Highlights & Scope:

  • 1 mile of selective tree cutting & logjam removal
  • 2 miles of complete ditch reconstruction w/associated clearing & grubbing
  • 10,000 CY of excavating & grading
  • Reconstruction of two lateral ditches/roadside swale
  • Includes culverts, erosion control structures, rock placement, and seeding/mulching

STEINLE DITCH

NEW WATERWAY

Project Highlights & Scope:

  • Construct 4 acre waterway, complete with seed & mulch and erosion control blanket
  • 8,000 CY of excavating & grading
  • Haul & Place 110 ton of Type C rip rap
  • Install 43,200 SF of 16’ wide erosion control blanket

DUSTY ACRES DITCH

OPEN DITCH

Project Highlights & Scope:

  • 56,000 CY of Excavation & Grading
  • Clearing & Piling of 6 miles of heavy trees & brush
  • Grading across 50 acres of farm ground
  • Clean 11 culverts & bridges
  • Seed 20 acres of ditch bank
  • Misc. Tile Repairs & Extensions

FORT JENNINGS STATE BANK

BUILDING DEMOLITION & SITE PREP

We were fortunate to be the demolition subcontractor on this local project that involved complete
demolition and subsequent removal of the existing Fort Jennings State Bank. This bank was constructed
in 1970 by Nolan’s Grandpa Bill ‘Banker Bill’ Wildenhaus...

GRESSEL DRIVE - WATERLINE

WATERLINE REPLACEMENT

Project Highlights & Scope:

  • Installation of 890 LF of C900 Waterline
  • (4) 45 Degree Bends
  • Pressure Test & Chlorinate the line
  • Expose, isolate, plug, and retest the line
  • Remove the plugs and reconnect to the existing lines using (3) solid sleeves

LAMB DITCH

STORM SEWER/TILE DITCH

Project Highlights & Scope:

  • 400 LF of 8” Storm Sewer
  • 335 LF of 15” Storm Sewer
  • Remove & Replace one Catch Basin
  • Install 2 new Catch Basins
  • Place 10 CY of Type C Rip Rap
  • Final Grading, Seeding, and Restoration
TOP